Inspection Reports for
Lake Chabot Care Home
2723 Barlow Dr, Castro Valley, CA 94546, USA, CA, 94546
Back to Facility ProfileDeficiencies (last 2 years)
Deficiencies (over 2 years)
0 deficiencies/year
Deficiencies are regulatory violations found during state inspections.
Same as California average
California average: 4 deficiencies/yearDeficiencies per year
4
3
2
1
0
Occupancy
Latest occupancy rate
33% occupied
Based on a January 2026 inspection.
This facility has shown a decline in demand based on occupancy rates.
Occupancy rate over time
Inspection Report
Annual Inspection
Census: 2
Capacity: 6
Deficiencies: 0
Date: Jan 16, 2026
Visit Reason
The inspection was an unannounced 1-Year Annual Required inspection conducted to evaluate compliance with licensing requirements.
Findings
The facility was found to be in full compliance with no deficiencies cited. The environment was safe and well-maintained, resident records and staff records were complete, and safety equipment was operational.
Report Facts
Hot water temperature: 118.8
Fire extinguisher last serviced: Mar 2, 2025
Emergency Disaster Plan last posted: Jan 1, 2026
Emergency disaster drill last conducted: Jan 2, 2026
Residents records reviewed: 2
Staff records reviewed: 5
Employees mentioned
| Name | Title | Context |
|---|---|---|
| Andrei Joseph | Care Staff | Met with Licensing Program Analyst during inspection |
| Navraj Brar | Administrator | Facility administrator not present during visit |
| Ardalan Gharachorloo | Licensing Program Analyst | Conducted the inspection |
| Yvonne Flores-Larios | Licensing Program Manager | Named in report header |
Inspection Report
Original Licensing
Census: 6
Capacity: 6
Deficiencies: 0
Date: Jan 31, 2025
Visit Reason
The inspection was conducted as a pre-licensing visit due to a change in ownership (CHOW) of the facility.
Findings
The Licensing Program Analyst toured the facility and found all areas compliant with safety and comfort standards, including adequate lighting, temperature, and safety equipment. Resident and staff records were complete, and no issues were noted during the inspection. The facility was observed to be ready for licensing, pending final approval.
Report Facts
Hot water temperature: 111
Facility capacity: 6
Census: 6
Employees mentioned
| Name | Title | Context |
|---|---|---|
| Navraj Brar | Administrator | Facility Administrator met during inspection and discussed purpose of visit |
| Ardalan Gharachorloo | Licensing Program Analyst | Conducted the pre-licensing inspection |
| Yvonne Flores-Larios | Licensing Program Manager | Named as Licensing Program Manager on report |
Inspection Report
Census: 6
Capacity: 6
Deficiencies: 0
Date: Jan 31, 2025
Visit Reason
The visit was a Case Management - Other type of unannounced inspection conducted by a Licensing Program Analyst.
Findings
The Licensing Program Analyst conducted Component III with the Administrator and presented a related power point presentation. A copy of the report was provided to the Administrator.
Employees mentioned
| Name | Title | Context |
|---|---|---|
| Navraj Brar | Administrator | Met with during Component III presentation and inspection. |
| Ardalan Gharachorloo | Licensing Program Analyst | Conducted Component III and presented power point presentation. |
| Yvonne Flores-Larios | Licensing Program Manager | Named as Licensing Program Manager on report. |